Pipe Installation Along Brownwood Road Complete, Water Intake Project Update #10

Last Updated on December 22, 2017 6:06 pm

All pipe installation along Brownwood Road is complete by the Garney Construction Company, according to the Town of Boone.

The Town says the patches were to be completed this week and milling/overlay will be complete next spring. Trenchless crossing #4 under the New River at New River Hills is complete and tied into the new water main line. Crews are working on trenchless crossing #5 near the New River bridge at HWY 421.

On Feb. 13, 2017 the Harper Corporation and Garney Construction Company, Inc. were provided with the Notice to Proceed on the Boone Water Line, Water Treatment Plant, Intake and Booster Pump Station Project. There are currently 246 days remaining in the project contracts.

The Harper Corporation continues to complete items at the water treatment plant, the water intake site and at the Brownwood Road booster pump station. Dewatering systems remain in place and in operation at the intake site. Road construction into the intake site is nearing completion. Preparation and excavation for the wet well at the intake is underway.